Construction site
|
Vetrocom Buzludzha: Installation of wind farm with 29 wind turbine generators of 2.5 MW Construction site altitude – 1400 meters Total capacity of installed power: 72,5 MW The design project is developed by Fuhrlander, Germany. Contracting authority: Vetrocom Ltd. |
|
Construction works
|
Construction of engine seating for 29 wind turbine generators and all necessary crane plots and loading platforms In 2009 – installation of 20 wind turbine generators of 2.5 MW In 2011 – installation of 9 wind turbine generators of 2.5 MW - 2011 г. Total amount of reinforcement - 1 450 t Total amount of concrete - 11 220 м3 Complete installation of internal electric networks - 48 km (cable line with middle voltage, diameter 120-140 mm2); external electric networks – 9 km (from substation 20/110kv to overhead lines 110kv, realized with ABB cable 110kv type AXLJ 1x400/40) and communication cable routing – 38 km (optic underground cables laying between generators and pulled out along the overhead line 110kv).
|
|
Construction site
|
Photovoltaic park, village of Samovodene, 3 MW
|
| Construction works |
Construction of foundations; assembly of metal structure and PV panels Construction of cable lines and premises; installation of high voltage equipment, transformers and invertors |
 |
Construction site
|
Photovoltaic park, village of Zlataritsa, 21 MW
|
| Construction works |
Excavation works for vertical planning - 1 100 000 м3 |
|
Construction site
|
Photovoltaic park, village of Ostar kamak, region of Harmanli, 5 MW Excavation works for vertical planning – 250 000 м3 Contracting authority: SUNDAY SDN, Korea
|
|
Construction works
|
Construction of foundations; assembly of metal structure and PV panels Construction of cable lines and premises; installation of high voltage equipment, transformers and invertors
|
|
Construction site
|
EVN Distribution Company Bulgaria, Stara Zagora |
|
Construction works |
Framework Contract for construction, wiring and excavation works and repairs on the territory of the Client Energy Centers in Stara Zagora, Chirpan and Zagore (external power supply of buildings, construction of tube, cable and overhead lines low and middle voltage; construction of concrete, metal and mast transformer stations)
|
|
Construction site
|
Park Mall Plovdiv Contracting authority: Instroy Ltd. |
|
Construction works |
Construction of electric installations and terminals for power supply to temporary switchboards at a total amount of 16 081.53 €
|
|
Construction site
|
Park Mall: External power supply of Shops & Entertainment Center with underground parking by a transformer station
Project amount: 287 487.89 € Contracting authority: Eurobuild Ltd.
|
| Construction works |
Installation of external power supply, cables, tube lines, transformers and supply with transformer station equipment
|
|
Construction site
|
Shopping Center, Parvomay: Overhaul, reconstruction and construction Project amount: 219 558.30 BGN. Contracting authority: Adelmax Ltd. |
|
Construction works |
Destruction of the old building; excavation works (excavation, transportation, gravel-embankment, consolidation and vertical planning). Construction of external and internal sewerage, water-conduit, power supply installation and fire alarm system
|
|
Construction site
|
Logistic Center Project amount: 76 726.34 € Contracting authority: Logistic BG Ltd. |
|
Construction works |
External and internal power supply (supply and pulling out of cables middle and low voltage /type abbreviation CVT, PBB-MB1, UTP/, industrial and public lightning, etc.); water-supply network, sewerage, fire alarm system, geodesic surveying and vertical planning.
|
|
Construction site
|
Knauf Bulgaria: Construction of road connection from III-5504, km 4+950 to Knauf gypsum factory km 0+000 to km 1+900. Project amount: 1 108 184.55 € Contracting authority: Municipality of Galabovo (tender procedure award) |
| Construction works |
Construction and assembly works
|
|
Construction site
|
Knauf gypsum factory
Project amount: 221 584.61€ Contracting authority: Knauf Bulgaria Ltd.
|
|
Construction works |
Construction works, road construction, wiring, fence construction, routing of water and gas sewerage systems, technological works. Wiring consists in supplying and pulling out of plastic tubes in a trench, covering by sand, pulling out of cable type HH, installation of cable box 240мм2, etc.
|
|
Construction site
|
Medven Asphalt Works: Feeder cables low and middle voltage Project amount: 81 922.00 BGN Contracting authority: Stara Zagora Road Maintenance Company Ltd. |
|
Construction works |
Construction of tube network for cables, construction of concrete compact transformer station 20кV
|
 |
Construction site
|
Showroom, service-station and office-buildings located on the land of Stara Zagora, Chanlak country, property No 002489 Project amount: 141 510.00 BGN. Contracting authority: Autohit 2000 Ltd. |
| Construction works |
Supply and fitting, disassembly and assembly of cables, construction of concrete compact transformer station, etc.
|
|
Construction site
|
External wiring of photovoltaic turbine generators situated on the land of Sarnevo village, Cheliyata contry, property No 075011 Project amount: 30 665.00 € Contracting authority: Ecovat Ltd.
|
| Construction works |
Delivery and assembly of cables; construction of concrete compact transformer station, delivery and assembly of transformers, testing of high voltage cables, etc.
|
|
Construction site
|
Framework Contract for construction works in Mtel Shop Centers, Bulgaria Contracting authority: Mobiltel EAD |
|
Construction works |
Emergency and routine repairs in Mtel shop centers
|
|
Construction site
|
Stara Zagora Municipality Contracting authority: Municipality of Stara Zagora
|
|
Construction works
|
Road reconstruction; reconstruction of Stara Zagora bus station; reconstruction of tube networks of Bulgarian Telecommunication Company, EVN Bulgaria, Cable Tel company on the territory of Stara Zagora Municipality. |
|
Construction works
|
Installation and maintenance of a new public lightning in town of Stara Zagora Contracting authority: Hit Ltd.
|
|
Construction site
|
Park Mall Stara Zagora & Arena Cinema Contracting authority: Park Mall Stara Zagora; Arena Cinema |
|
Construction works |
External wiring and lightning
|
|
Construction site
|
PMU AD Project amount: 31 602.79 € |
|
Construction works |
Power supply of cathodic stations
|
|
Construction site
|
Supermarket Billa Dimitrovgrad Excavation works and vertical planning
|
|
Construction works |
Ministry of Labour and Social Policy
Reconstruction of the regional office-buildings in town of Stara Zagora
|
|
Construction site |
Hypermarket Praktiker
Project amount: 222 300.00 BGN
|
|
Construction works
|
External power supply of Hypermarket Praktiker Stara Zagora; pulling-out of cables 20 kV, assembly of transformers, installation of commutation distribution devices 20 kV |
|
|
Central Railway Station Sofia
Project amount: 236 106.00 BGN Contracting authority: Railway Infrastructure National Company, Energy Department, Sofia
|
|
Construction works
|
Reconstruction of the station platforms’ lighting
|
|
Construction site
|
Horizont – Ivanov Ltd.
Project amount: 107 416.88 € Contracting authority: Horizont – Ivanov Ltd.
|
|
Construction works
|
Buildings demolition; foundations and shafts removal; breaking of the concrete waste in fractions; separate waste collection
|